Ibis Adelaide Hotel - Construction Update

At 17 levels, the structure of Ibis Adelaide is now complete. The project team celebrated this milestone with the customary “topping off” ceremony, hoisting a tree to the roof of the completed structure.

As construction advances towards completion, up to 150 people are working on site each day. On every level of the building a different team of tradespeople are busy at it cycling through the floors. Partitioning has progressed to level 16, with wall linings now up to level 11. Tiling works are up to level 7 and painters are already on level 8.

The curtain wall glazing system is being installed as high as level 14.

The illuminated feature stair which will sit in the void between the ground floor lobby and the food and beverage spaces on level 1 is schedule to be installed during this month.

The tower crane is scheduled to be removed during April.

Further updates to follow.